REVERSE OSMOSIS WATER TREATMENT PLANT

At the end of 2019, the Town of Churchbridge was the recepient of a Government grant towards the upgrading of the Water Treatment Plant to a Reverse Osmosis Plant. In October 2020, construction officially began with an operational target date of May 2021.

PROGRESS

November 2020
The dirt was pulled away from the reservoir and the cement cleaned off.





December 2020
The walls of the addition were erected



January 2021
Construction of the rafters was completed.



 


February 2021


























     
- Ph: 306-896-2240 - Email: churchbridge@sasktel.net - Town Office: 116 Vincent Ave. W. - Box 256 - S0A 0M0 - www.churchbridge.com -